Construction & Development

Opinion: 335 Homes Cover 1.1 Percent of the 30 by 30 Target

335 homes at $922,388 each cover 1.1 percent of the city's 30,000-resident target. The services model works at block scale, and the per-home cost is the figure the recovery argument has to answer.

The test case

The 151-unit senior building on Folsom Street carries 30 homes for residents who have been homeless. Measure that block against the city's target of 30,000 downtown residents and students by 2030. The arithmetic answers the claim that subsidised housing can carry downtown recovery.

335 homes against 30,000

Block 2 delivers 335 homes. Philip C. Chin Commons holds 151 and the family tower holds 184. The city set the 30 by 30 goal in its March 2024 State of the City address and needs about 370 residents a month from that date to the end of 2030.

Block 2 supplies 1.1 percent of the target. Ten blocks of this size would reach 3,350 homes, and the city would need roughly ninety of them to house 30,000 people. Block 2 took 26 months from groundbreaking to its first permit final.

What the city spent per home

The Mayor's office put the combined budget at $309 million, or $922,388 a home across 335 homes. The permit valuations tell a narrower story. The Department of Building Inspection values the senior building's construction at $56,977,150 and the family building at $74,471,078, or $392,383 a home combined. The gap covers land, design, fees and financing, and it belongs in any comparison.

The family tower carries its own published ratio. In April 2024 the Board of Supervisors voted on a $115,845,218 construction loan to Mercy Housing, which covered 61.3 percent of an estimated $189 million budget and works out to nearly $1.03 million a home. Any argument for subsidised housing as a recovery engine has to answer that figure.

The services model earns its cost

The case for the block rests on the services. Chinatown Community Development Center runs intensive care management on site. Sixty of the 151 homes serve extremely low-income residents on fixed incomes, and thirty serve people who were homeless. A building that holds those households in place for years does work a shelter cannot do, on a parcel that carried a community room and a surface car park until 2024.

The record publishes no staffing plan, no wage figure and no operating budget for those services. A public commitment to care management carries an annual cost that nobody has published.

Retail at fifteen square feet a home

The street-level programme is small. The senior building carries 3,000 square feet of ground-floor retail and the family building adds 1,960 square feet of community-serving retail, or 14.8 square feet per home across 335 homes. The 6,480-square-foot childcare centre serviced by Wu Yee is the stronger asset of the three, because it serves working households across the district. The record names no retail tenant and publishes no rent for either bay.

The market-rate pipeline stalled first

Hines pursued a 47-story tower at Transbay Block 4 with 681 apartments. In June 2024 the firm missed a payment to the Office of Community Investment and Infrastructure and lost its exclusive option. The city then began a search for a developer to build between 300 and 325 affordable units on Block 4 West.

The subsidised building finished while the market-rate block stalled. The recovery therefore ran on the public side, at $922,388 a home on the Mayor's own figure.

Where the recovery claim fails

A ten-story residential block on a third of an acre adds residents at income bands that generate little property tax and no commercial rent at scale. The senior building closed its permit on 17 July 2026, and its 151 homes sit one block from Salesforce Park. Those residents will shop locally and ride transit. That is neighbourhood value.

Neighbourhood value does not fund city services. A downtown that carries its own budget needs offices let at market rents, hotels at published rates and market-rate homes on the tax roll. Block 2 adds residential capacity and no commercial rent.

The verdict

Build it, and build the next one the same way. The services model, the 30 set-asides and the childcare centre are the right ingredients, and the July 2026 sign-off proves the delivery path works. Then stop selling that model as a downtown recovery strategy. 335 homes against a 30,000 target is 1.1 percent, and the per-home cost on the city's own budget figure is $922,388.

San Francisco should price the next ninety blocks before it promises the next 30,000 residents.