The Blue Line's Award Record and the Hotels on Washington Street

IndyGo awarded almost $250 million across three Blue Line packages in December 2024 for a late-2028 opening. The Washington Street frontage gives up drive-up arrival and self-parking access for the duration of the build.

The award record

IndyGo’s Board of Directors awarded almost $250 million in construction contracts for the Blue Line on 19 December 2024. Three central Indiana firms took one package each.

Gradex Inc. holds Package A at approximately $208 million. The package covers stormwater and drainage improvements, pavement resurfacing, pedestrian facilities, traffic signal upgrades and sanitary sewer relocations. F.A. Wilhelm Construction Co. holds Package B at approximately $34 million for the stations, after building the Red Line and Purple Line stations. R.L. Turner Co. holds Package C at approximately $6 million for the East Side Mobility Hub, an offsite transfer facility at the east end of the project.

The federal side carries a $150 million Small Starts grant from the Federal Transit Administration and almost $22 million from the RAISE programme. IBJ reported the wider split on 1 March 2025: $207.8 million in grants and federal funding, a $135 million IndyGo match, $16.5 million from the Department of Public Works and $15 million from Citizens Energy Group.

The project page sets the sequence. Design finished in September 2024, groundbreaking came in February 2025, construction began in the second quarter of 2025, and the line opens in late 2028. The route runs 24 miles from Indianapolis International Airport to the town of Cumberland along I-70, Holt Road and Washington Street, with 30 stations at half-mile to one-mile spacing.

What the corridor commits the frontage to

Construction impacts run from 2025 through 2028 in 12 areas. The current segment list is the operating document for a hotel on Washington Street.

Maryland and Washington streets from West Street to Capitol Avenue carry lane closures for curb ramps, pedestrian improvements and station construction, with a minimum of one lane maintained in each direction. Work is in progress on the future Statehouse Station at Washington Street and Capitol Avenue and on the future Convention Center Station at Maryland Street and Capitol Avenue. The northern eastbound lane at the approach to Maryland and West streets is closed for the duration of the project, and one left-turn lane is maintained. The inside lanes are barriered from South White River Parkway to West Street for the Zoo Station and White River State Park stations.

West of downtown, westbound traffic has no access between Rockville Road and Belmont Avenue from on or after 14 September. The detour runs north onto North White River Parkway, west onto Michigan Street and south onto Holt Road. Eastbound access holds in a single lane. Further east, Washington Street closes to eastbound traffic between Emerson and Ritter avenues from on or after 1 November for approximately 160 days. Construction stops in Irvington from 1 to 31 October between Ritter Avenue and Ridgeview Drive.

IndyGo publishes each new closure one to three weeks ahead by weekly email. Local access to residences and businesses stays open through the work. Deaon Smith and Alexis Craft serve as neighbourhood liaisons during business hours, and Clarence Underwood holds the construction community outreach coordinator role. The project offers businesses an “Open for Business” signage and window-cling toolkit, a property access map and meetings with an IndyGo representative.

The concession the frontage carries

A hotel that fronts Washington Street sells its kerb. Drive-up arrival, taxi and rideshare pick-up and self-parking all depend on the lane configuration outside the door. For the duration of the work those hotels give up part of that access, and the station that replaces it arrives on the same schedule as the disruption.

Two future stations sit on hotel blocks. Statehouse Station is planned at Washington Street and Capitol Avenue, and Convention Center Station at Maryland Street and Capitol Avenue. The Indiana Convention Center counts 7,100 hotel rooms downtown and 4,700 rooms connected by skywalk. The line lowers the access cost between the airport and those rooms after 2028.

The inventory on the corridor

Washington Street carries the hotel stock the line serves. The addresses below come from OpenStreetMap records.

Hyatt Regency Indianapolis at 101 W. Washington Street. Embassy Suites by Hilton Indianapolis Downtown at 110 W. Washington Street. The Westin Indianapolis at 241 W. Washington Street. Fairfield Inn & Suites Indianapolis Downtown at 501 W. Washington Street. Courtyard Indianapolis Downtown and SpringHill Suites Indianapolis Downtown at 601 W. Washington Street. Hotel Indy at 141 E. Washington Street. La Quinta Inn & Suites at 401 E. Washington Street. Atlas Hotel at 433 E. Washington Street. Marriott Indianapolis Downtown at 350 W. Maryland Street sits beside the planned Convention Center Station.

The demand record

Bradford Allen’s Indianapolis market article of 19 March 2026 reports that the market recorded 8.1 million room nights of demand in the 12 months to mid-year 2025, on CoStar data. The figure sits more than 580,000 room nights above the market’s pre-COVID peak. The same article reports the Downtown Indy Alliance snapshot: 64.7 percent downtown occupancy against a 62.4 percent U.S. average, $135.20 in revenue per available room for a 13 percent year-over-year increase, and $209.11 in average daily rate for a 12 percent increase. The pipeline at mid-year held more than 1,500 rooms under construction, 3,402 rooms in final planning and 3,220 rooms proposed.

No published series ties that demand to transit. The line’s demand case rests on airport arrivals, on employees reaching shift work and on guests reaching the convention district without a car. A dedicated lane and level boarding lower the cost of those trips.

What settles the question

Six items would settle whether the corridor lifts performance. IndyGo publishes no month inside 2028 for the opening and no end-to-end airport running time. No publisher carries the mode share of airport arrivals to downtown hotels, a pickup figure by corridor frontage, ridership projections for the Statehouse and Convention Center stations, or a group fare and coach staging plan for the East Side Mobility Hub.

Price the disruption into the next two budgets and the access gain into the years after 2028. Ask IndyGo for the opening month, the running time and the station ridership projections.